Saturday, September 15, 2012

Projects - Trip to CA Aug 2012

t
Here is the garage that needed some help getting organized.
Here's the 8' long 8' tall storage rack - built using miter saw and circular saw.
Gates built in SD shop from recycled stair rails from Habitat for Humanity's RE-STORE.  Installed at bottom of stairs in Chino.

Gate built in SD - installed at top of stairs in Chino.
Garage just begging for a workbench.
Workbench for daughter, new grandson and old grandson.  Built from 8' section of reclaimed maple bowling alley that was demolished in 2007 in Riverside, CA.
Didn't take long to fill it up - added pagboard above workbench and small shelf for screws.
Toy box reclaimed from Goodwill in Denver, CO.  Repaired and restored in shop in SD.  Added "TOYS" to top, hinges to stop the oak lid from slamming on fingers, and grandsons names to underside of lid. Delivered to CHINO.
Project is to hang flat screen on the wall and build shelf under it for audio/video components.
TV Mounting Bracket is installed and shelf assembled and put in position..
Shelf is almost ready - made from reclaimed plywood and fancy carving.

Carving was 3" short of shelf - so added a 1 1/2" piece of mahogany to each end and it worked great!  Finished carving with wipe-on poly and painted underside of shelf black.
the end

Tuesday, June 19, 2012

BASEMENT FINISH - BOAT ROOM FLOORING

June 18, 2012:  Started laying the laminate flooring in the "Boatroom".  The pattern selected was SPALTED MAPLE.
First step was to put 3/8 " strips all around the perimeter of the room.  Found out later they should be attached pretty solidly, so that you can tap your pieces against them as you install them.  The strips are a "must" to the success of the project.
Then we installed the pad.  9 am to 11:30 am.  We had to piece it somewhat in the last corner.  We couldn't find any instructions in the boxes of flooring for some time - about the 5th box, we found a set of instructions.  It said to put down one strip of pad, then lay down the flooring, then add another strip of pad, and then lay down flooring, etc.   We put the pad down over the whole floor and then started laying the flooring.  Seemed to work okay anyways.





We started out with 10 boxes of laminate flooring - each piece is 7.5 inches x 50.5 inches.


 This took from 11:30 am until 2:30 pm.
 We got back to work after a long lunch - so worked from 5 pm til 8:30 pm.







 We stopped here for the day.  We have installed six boxes, with four boxes left.  We hope we have estimated correctly.  We have to lay 5 more strips at 19 ' each, which should give us several pieces to spare.


June 19, 2012 - 10 am to Noon - finished the last twenty or so pieces.  Here's the view looking into the room toward the closet and the book nook - with all but the little pieces left:

View looking out from the room toward the stairs:


One of the things that I didn't get a chance to read in the instructions ahead of this time was the Warning to make sure the last row would be more than 2.5 inches wide.  If it was going to be less, you can compensate for this by ripping a couple inches off the very first row.  This is very common practice in laying ceramic tile, but I managed to not remember this technique.   Unfortunately, my last row was between 1.25 inch wide to .625 inches wide.  This is not normally acceptable, but this small row will be covered by the base molding, so will not affect the look of the layout. 

Here's the view of the east wall before adding the tiny little strips to finish it off.

Here's the other place that needed a special cut - this piece was 1 3/8 inches wide.

Here's a view looking from the family room into the boat room.

Here's the east wall with the very tiny strips installed and glued.


Here's the view of the 1 3/8" strip in the book nook:


Kathie started bringing in samples of baseboard to see which would look best with the SPALTED MAPLE flooring:

Here's the left over pieces - 4 complete pieces and 4 with about a 1 inch strip ripped from the top side.  Note all the empty boxes stacked up - yahoo!


Here's the transition piece from the hallway ceramic tile to the laminate flooring:


Here's the transition piece from the laminate flooring to the ceramic tile in the closet.



Here's the completed flooring for the BOAT ROOM as viewed from the hallway:

So now to complete the other remaining tasks in the room, we will need to install door casings (2 doors),  paint the door casings, stain and seal the baseboard molding and cove, install the baseboard molding and cove, install a coax connector, install an ethernet connector on the 8 wire cable, and build/install the closet shelf and clothes rack.

----------------------------------------------
And in the meantime, there is another project to work on - assembling the Father's Day BBQ!




the end

Wednesday, May 16, 2012

Re-roofing Project - Day 2 - May 16, 2012

Results from first day of work (11:30 am to 7:00 pm):
House - all old shingles/metal removed;  east side about 3/4 of shingles replaced;  west side - tar paper in place, Shop - all old shingles/metal removed; about 3/4 of shingles replaced;  center shop all shingles removed, about 1/2 shingles replaced.  Garage - not started yet.



 Is that a fiddler on the roof?







 Second day - Garage started.  House shingles almost all replaced.  Shop Shingles - most all replaced.

 View from the SEWING ROOM

Update - May 16, 2012 -  7 pm - both shop/garage and house re-roofing is complete with new shingles and metal.  The GUTTER/DOWNSPOUT GUYS will be here tomorrow.
the end