Results from first day of work (11:30 am to 7:00 pm):
House - all old shingles/metal removed; east side about 3/4 of shingles replaced; west side - tar paper in place, Shop - all old shingles/metal removed; about 3/4 of shingles replaced; center shop all shingles removed, about 1/2 shingles replaced. Garage - not started yet.
Is that a fiddler on the roof?
Second day - Garage started. House shingles almost all replaced. Shop Shingles - most all replaced.
View from the SEWING ROOM
Update - May 16, 2012 - 7 pm - both shop/garage and house re-roofing is complete with new shingles and metal. The GUTTER/DOWNSPOUT GUYS will be here tomorrow.