Re-roofing Project - Day 2 - May 16, 2012

Results from first day of work (11:30 am to 7:00 pm):
House - all old shingles/metal removed;  east side about 3/4 of shingles replaced;  west side - tar paper in place, Shop - all old shingles/metal removed; about 3/4 of shingles replaced;  center shop all shingles removed, about 1/2 shingles replaced.  Garage - not started yet.



 Is that a fiddler on the roof?







 Second day - Garage started.  House shingles almost all replaced.  Shop Shingles - most all replaced.

 View from the SEWING ROOM

Update - May 16, 2012 -  7 pm - both shop/garage and house re-roofing is complete with new shingles and metal.  The GUTTER/DOWNSPOUT GUYS will be here tomorrow.
the end